Badan Pengurusan Bersama Tasik Heights Apartment v ASM Development Sdn Bhd [2026] CLJU 280 | High Court of Malaya
Facts
The Plaintiff, Badan Pengurusan Bersama Tasik Heights Apartment (the JMB), was formed on 17 May 2008 to manage the Tasik Heights Apartments following the completion of the project. The Defendant, ASM Development Sdn Bhd, was the registered owner developer who had sold the apartments to purchasers in or around 1992 under Housing Developers (Control and Licensing) Regulations 1989, Schedule H Sale and Purchase Agreements.
After the JMB assumed management, it discovered that the Developer had never applied for nor obtained separate strata titles for the individual purchasers, despite decades having passed since the original sales.
In July 2020, the Land Office approved an amendment to the express condition on the land and required the Developer to pay further land premiums within six months before any subdivision application could proceed. The Land Office subsequently granted multiple extensions of time, including extensions attributable to the COVID-19 pandemic, with the final deadline falling in December 2022.
Despite repeated reminders and a formal demand issued by the JMB on 31 December 2022, the Developer failed to pay the required premiums. The JMB filed an Originating Summons in October 2023 to compel the Developer to comply.
Issues
- Does the Developer owe a statutory duty (as opposed to a purely contractual duty) to apply for subdivision and procure individual strata titles for the purchasers under the Strata Titles Act 1985?
- Does the JMB have locus standi to enforce this obligation against the Developer under the Strata Management Act 2013?
Decision and Reasoning
The Developer’s Statutory Duty
The High Court held that the Developer is under a statutory obligation pursuant to sections 8(1), 8A(1), 8(3) and 9(1) of the Strata Titles Act 1985 to apply for subdivision of the land, pay the requisite land premiums, and procure the issuance of separate strata titles for the parcel owners. This duty arises by operation of statute, not merely from the terms of the Sale and Purchase Agreements.
Privity of Contract Defence Fails
Accordingly, the Developer’s privity of contract defence — namely that the JMB was not a party to the original SPAs and therefore could not enforce the agreements — failed. The JMB’s claim was founded on breach of statutory duty, which does not require privity of contract.
The JMB’s Locus Standi
The Court found that the JMB has clear locus standi under sections 21 and 143 of the Strata Management Act 2013 to institute proceedings in connection with common property. The Court observed that the subdivision of the land into individual strata titles is essential for the JMB to properly carry out its statutory functions including imposing charges, maintaining the register of parcel owners, and managing the building and common property effectively. It follows that the JMB’s standing to sue is not contingent on any direct contractual relationship with the Developer.
Administrative Extensions Provide No Shield
The Court further found that the multiple extensions of time granted by the Land Office, including those arising from COVID-19, afforded the Developer no protection from court-ordered compliance. The statutory obligation remained subsisting and enforceable.
Orders Made
- Pay the outstanding land premiums required by the Land Office; and
- Complete and settle the subdivision application to procure individual strata titles for the parcel owners.
Costs of RM7,000 were awarded to the Plaintiff JMB.
Key Takeaways
- Statutory duty does not expire with time. A developer’s obligation under the Strata Titles Act 1985 to apply for subdivision and issue strata titles to purchasers is not extinguished by the passage of time. Developers cannot escape liability simply because decades have passed since the original sales.
- JMBs and JMCs have independent standing to sue. Joint Management Bodies and Joint Management Committees have clear locus standi under the Strata Management Act 2013 to enforce a developer’s statutory duties, even where the JMB was not party to the original Sale and Purchase Agreements.
- Privity of contract is not a bar to statutory duty claims. Where a claim is framed as a breach of statutory duty, the Developer’s privity of contract defence is unavailable. Purchasers and their management bodies need not rely solely on contractual remedies when the relevant legislation imposes a direct statutory obligation.
- Administrative extensions do not insulate developers from court orders. Multiple extensions granted by the Land Office do not shield a developer from judicial enforcement. The Court is not bound by the executive’s accommodation of a developer’s delays.
- Practical significance for strata communities. JMBs are empowered to resort to Originating Summons proceedings as a practical enforcement mechanism without needing to trace individual purchasers or rely on the original SPAs.
The above is for general information only and does not constitute legal advice. For advice specific to your situation, please consult a qualified lawyer.

Leave a Reply